和平水库坝址坝型比选及坝体结构设计

占美群 刘星波 王永东

云南水力发电2024,Vol.40Issue(7):72-74,83,4.
云南水力发电2024,Vol.40Issue(7):72-74,83,4.DOI:10.3969/j.issn.1006-3951.2024.07.018

和平水库坝址坝型比选及坝体结构设计

Comparison and Selectionof Dam Site and Dam Type and Structural Designof Dam Body in Heping Reservoir

占美群 1刘星波 1王永东2

作者信息

  • 1. 山东省水利勘测设计院有限公司贵州分公司,贵州 贵阳 550081
  • 2. 四川大学水利水电学院,四川 成都 610065
  • 折叠

摘要

Abstract

The comparison and selection of dam type at the dam site is an important part of the reservoir hub design.The determination of dam site and the selection of dam type have a great impact on the project investment and quality safety.In view of the unfavorable geological problems such as strong karst strata in the dam section of Heping reservoir,which are prone to river bed leakage,and considering the reservoir forming conditions,water storage capacity,hydroproject layout,construction conditions and other factors,the lower dam site face rockfill dam is designed and optimized.The analysis shows that the lower dam site has strong water storage capacity and stable reservoir bank,which is conducive to the layout of CFRD hub.Although the amount of anti-seepage works is slightly larger than that of core wall dam,the suitability of CFRD dam type is strong,and the investment economic benefit is good.

关键词

建坝河段/坝址确定/坝型比选/和平水库

Key words

dam section/determination of dam site/dam type comparison and selection/Heping Reservoir

分类

建筑与水利