| 注册
首页|期刊导航|北京水务|基于PS-InSAR密云水库大坝及周边山体垂直位移监测研究

基于PS-InSAR密云水库大坝及周边山体垂直位移监测研究

张丽娟 李宾 王琪 周上梯 于茜 王鹏宇 齐烁 刘宁

北京水务Issue(3):78-84,7.
北京水务Issue(3):78-84,7.DOI:10.19671/j.1673-4637.2024.03.015

基于PS-InSAR密云水库大坝及周边山体垂直位移监测研究

Research on vertical deformation monitoring of the dam and surrounding mountains of the Miyun Reservoir based on PS-InSAR

张丽娟 1李宾 1王琪 2周上梯 1于茜 1王鹏宇 1齐烁 1刘宁1

作者信息

  • 1. 北京市密云水库管理处 北京 101500
  • 2. 北京市水务规划研究院 北京 100017
  • 折叠

摘要

Abstract

Miyun Reservoir is a large-scale water conservancy hub project that combines flood control,irrigation,water supply,and power generation.As a reservoir for the South-to-North water diversion proj-ect,it plays a critical role in water regulation and storage,and is crucial for ensuring the capital's water security.However,with the increase in water from the south,the continuous high water level operation of Miyun Reservoir presents a significant challenge to the safe operation of its main and auxiliary dams.Uti-lizing PS-InSAR technology to capture deformation data of the dam body and surrounding areas of Miyun Reservoir,and conducting deformation monitoring analysis,is crucial for understanding the engineering behavior and potential issues of the main and auxiliary dams under high water conditions.The results in-dicate that the deformation data from PS-InSAR align closely with manual observations,with prominent subsidence occurring on the reservoir's southwest and south sides.The vertical deformations of the three dams exhibited a slight downward trend as the reservoir's water level gradually rose.This experiment of-fers significant reference value for the application of PS-InSAR in dam deformation monitoring.

关键词

变形监测/PS-InSAR/大坝变形

Key words

deformation monitoring/PS-InSAR/dam deformation

分类

交通工程

引用本文复制引用

张丽娟,李宾,王琪,周上梯,于茜,王鹏宇,齐烁,刘宁..基于PS-InSAR密云水库大坝及周边山体垂直位移监测研究[J].北京水务,2024,(3):78-84,7.