广东水利水电Issue(7):30-33,41,5.
整体全钢浮式系船柱埋件在白石窑枢纽船闸工程中的应用
Application of Integral All-steel Floating Bollard Embedment in Baishiyao Hub Lock Project
郭少斌1
作者信息
- 1. 广东省水利水电第三工程局有限公司,广东 东莞 523710
- 折叠
摘要
Abstract
The traditional bollard embedment is carried out by reserving the second-phase slot for the second-phase construction,which requires setting up scaffolding for the second-phase slot,chiseling the second-phase slot,tying reinforcing bars,installing formwork,pouring concrete and other processes,which consumes a lot of materials,labor,and has a large impact on the construction period.In view of the above problems,an integral all-steel floating bollard embedded device is proposed,which has achieved good results in the construction of floating bollard embedded in the second line of locks of Baishiyao Hub and the demolition and reconstruction of the first line of locks of Baishiyao Hub,and effectively overcame all the shortcomings of the traditional bollard embedded in the second-phase construction.关键词
整体全钢浮式系船柱埋件/船闸Key words
integral all-steel floating bollard embedment/ship lock分类
交通工程引用本文复制引用
郭少斌..整体全钢浮式系船柱埋件在白石窑枢纽船闸工程中的应用[J].广东水利水电,2024,(7):30-33,41,5.