广东水利水电Issue(7):34-41,8.
基于MIKE模型的溃坝洪水分析
Dam Break Flood Analysis Based on DHI MIKE:
洪敏绮 1周水兵 1罗学宁 1林波 2周佳麒 2傅举鹏 2蔡瀛2
作者信息
- 1. 南方电网调峰调频发电有限公司运行分公司,广州 511499
- 2. 广东省水利电力勘测设计研究院有限公司,广州 510635
- 折叠
摘要
Abstract
Taking Fanjiatian Reservoir in the upper reservoir of Huizhou pumped storage power station as the research object,the MIKE model and GIS technology are used to construct the one-dimensional mathematical model of Xiaojin River network,the two-dimensional mathematical model of water flow in Huicheng District and the coupling model of one and two dimensions.The combination of different working conditions is analyzed to evaluate the dam break flood risk in Huicheng District downstream of Fanjiatian Reservoir.The inundation depth map,inundation duration map,arrival time map and inundation range map are also drawn.It provides scientific and powerful support for the decision of dam break flood risk forecast and early warning in Huizhou pumped storage power station.关键词
MIKE模型/洪水风险图/抽水蓄能电站/溃坝分析/广东省Key words
DHI MIKE/flood risk maps/pumped storage power station/dam break analysis/Guangdong Province分类
建筑与水利引用本文复制引用
洪敏绮,周水兵,罗学宁,林波,周佳麒,傅举鹏,蔡瀛..基于MIKE模型的溃坝洪水分析[J].广东水利水电,2024,(7):34-41,8.