基于复杂网络的斜(竖)井施工事故致因分析OACHSSCD
Causes of Construction Accidents in Inclined(Vertical)ShaftsBased on Complex Network
为探究斜(竖)井施工事故风险演化路径、确定关键致因因素.首先,运用扎根理论对事故调查报告进行三级编码,明确斜(竖)井施工事故致因因素.其次,基于复杂网络理论,将致因因素作为网络节点,因素之间的相关关系作为网络连边,构建斜(竖)井施工事故致因网络.然后,利用Gephi软件实现致因网络可视化.最后,通过分析节点度、接近中心度、聚类系数等拓扑参数来反映网络的整体特性和确定影响斜(竖)井施工事故的关键致因因素.结果表明:该网络整体上聚类较好、平均路径较短,各风险因素间联系紧密,易发生连锁反应.经过或进入危险区域、机器设备失稳倾倒、不良地质、对"三违"情况制止不力等是斜(竖)井施工事故关键致因因素.
To explore the risk evolution path of inclined(vertical)shafts construction accidents and i-dentify key contributing factors,Firstly,the grounded theory is used to code the accident investigation report at three levels and clarify the causal factors of inclined(vertical)shafts construction accidents.Secondly,based on theory of complex networks,the causal factors are treated as network nodes,and the correlation between factors is used as network edges to construct a causal network for inclined(verti-cal)shafts construction accidents.Then,Gephi software was used to visualize the causal network.Fi-nally,topological parameters such as node degree,proximity to the centre and clustering coefficient are analyzed to reflect the overall characteristics of the network and to identify the key causal factors affect-ing the construction accidents in inclined(vertical)shafts.The results indicate that the overall cluste-ring of the network is good,the average path is short,and the risk factors are closely related,making it prone to chain reactions.Passing through or entering hazardous areas,unstable dumping of machinery and equipment,poor geology,and inadequate prevention of"three violations"are key contributing fac-tors to inclined(vertical)shafts construction accidents.
康小龙;李兆宇;任慧娜;张胜平;侯晓斌;张娟国
中国水利水电第三工程局有限公司,陕西西安 710016西安科技大学安全科学与工程学院,陕西西安 710054
安全科学
斜(竖)井施工扎根理论复杂网络事故致因网络关键致因因素
inclined(vertical)shafts constructiongrounded theorycomplex networkaccident causal networkskey causal factors
《技术与创新管理》 2024 (004)