| 注册
首页|期刊导航|陕西水利|深埋隧洞强岩爆段水锤钻机超前应力释放试验研究

深埋隧洞强岩爆段水锤钻机超前应力释放试验研究

麻蓉 黄瑜潇 李雄 齐国庆

陕西水利Issue(8):144-148,5.
陕西水利Issue(8):144-148,5.

深埋隧洞强岩爆段水锤钻机超前应力释放试验研究

Experimental Study on Advanced Stress Release of Water Hammer Drilling Rig in Strong Rock Burst Section of Deep Buried Tunnel

麻蓉 1黄瑜潇 1李雄 1齐国庆1

作者信息

  • 1. 陕西省引汉济渭工程建设有限公司,陕西西安 710010
  • 折叠

摘要

Abstract

Rock burst is a world problem in the geological discipline of deep buried tunnel.The advance drilling of rock mass can release the internal stress of surrounding rock structure and reduce the grade and frequency of rock burst in the process of excavation disturbance.Through the space calculation of the drilling range and the optimization and modification of the drilling arm,the advanced stress release test of the water hammer drilling rig was carried out on the strong rockburst section during the TBM process of YinhanJiwei lingnan.The energy values of the microseismic monitoring system before and after the field test were compared.The results show that the advanced stress release of the water hammer drilling rig can reduce the grade,strength and damage range of the rockburst to a certain extent,reduce the amount of support engineering,and reduce the probability of delayed rockburst.It can provide reference for the subsequent construction and similar projects of TBM rockburst excavation section with increasing buried depth.

关键词

岩爆/深埋隧洞/水锤钻机/微震监测/应力释放

Key words

Rock burst/deep buried tunnel/water hammer drilling rig/microseismic monitoring/stress release

分类

建筑与水利

引用本文复制引用

麻蓉,黄瑜潇,李雄,齐国庆..深埋隧洞强岩爆段水锤钻机超前应力释放试验研究[J].陕西水利,2024,(8):144-148,5.