摘要

Abstract

The existing large wharves in Qinzhou port belongs to gravity structure.Based on jetty No.19 in Jingujiang operation area,the key technical issues and countermeasures were discussed,which were related to the execution of the first large piled beam-slab wharf in this region,the statistics of real effects were made and analyzed.Such a new wharf structure served as a technical reference,which was beneficial to the port development.The adaptability of piled structure was analyzed,the main difficulties during construction were highlighted,including the application of a new technology of drilling&piling,which solved the difficulty of driving temporary auxiliary steel tubular pile and steel casing into the rock exposed to air in deep water environment.And the crossing construction mechanism of rock blasting and cast-in-situ pile was studied for the first time,which served as a new engineering case.The safety control requirements corresponding to the new structure were put forward,which supplemented local safety education.

关键词

高桩梁板码头/引孔植桩/灌注桩/炸礁/交叉施工/安全管理

Key words

beam-slab structure on piles/drilling&piling/cast-in-situ piles/rock-blasting/crossing construction/safety control

分类

交通工程

引用本文复制引用

韦学敏,许建武..钦州港首座大型高桩梁板码头建设关键技术与对策[J].港口航道与近海工程,2024,61(4):93-96,101,5.

基金项目

国家自然科学基金面上项目:海上丝绸之路港口的港湾共振及其引起的系泊船响应研究(52071060) (52071060)

港口航道与近海工程

1004-9592

访问量0
|
下载量0
段落导航相关论文