| 注册
首页|期刊导航|广东水利水电|水电站溢洪道高架塔机拆除施工技术

水电站溢洪道高架塔机拆除施工技术

王永周 魏永政 王亚萍 刘斌 马旭

广东水利水电Issue(8):95-101,7.
广东水利水电Issue(8):95-101,7.

水电站溢洪道高架塔机拆除施工技术

Construction Technology of Elevated Tower Crane Demolition for Hydropower Station Spillway

王永周 1魏永政 1王亚萍 1刘斌 1马旭1

作者信息

  • 1. 中国水利水电第三工程局有限公司,西安 710024
  • 折叠

摘要

Abstract

In order to meet the bearing capacity and operating width of the 400t crane used for the dismantling of the elevated tower crane in the spillway of the Nantun 1 hydropower station,a simple supported beam was innovatively used to support the front legs of the downstream crane by pouring concrete on adjacent gate piers using a stacked beam gate on the free side downstream of the main dam;The downstream side rear support legs are supported by pouring concrete piers onto the spillway gate piers as a support platform;The upstream front support leg and the upstream rear support leg are both supported by laying I-beams on the top surface of the main body of the dam as a support platform;And use theoretical and numerical simulation methods to verify the safety of the supporting platform's bearing capacity.The results show that the supporting platform can meet the bearing capacity and operating width of a 400t crane when dismantling an elevated tower crane.The construction process and key points of dismantling are summarized,and the abandoned stacked beam gate is successfully used to dismantle the elevated tower crane of the spillway of Nantun 1 hydropower station,achieving good economic benefits.This provides a reference for the dismantling of tower cranes in high-altitude restricted environments and has important practical value.

关键词

水电站溢洪道/高空塔机拆除/支撑平台设计/吊车受力分析/有限元模拟

Key words

hydropower station spillway/demolition of high-altitude tower cranes/support platform design/crane force analysis/finite element simulation

分类

机械制造

引用本文复制引用

王永周,魏永政,王亚萍,刘斌,马旭..水电站溢洪道高架塔机拆除施工技术[J].广东水利水电,2024,(8):95-101,7.

基金项目

陕西省科技创新项目(编号:2022TD-01). (编号:2022TD-01)

广东水利水电

1008-0112

访问量0
|
下载量0
段落导航相关论文