山东煤炭科技2024,Vol.42Issue(8):185-190,6.DOI:10.3969/j.issn.1005-2801.2024.08.037
补连塔煤矿膏体充填环管输送试验研究
Experimental Study on the Transportation of Paste Filling Ring Pipe in Bulianta Coal Mine
田银素 1朱阳亚 2黄振华2
作者信息
- 1. 中国神华能源股份有限公司神东煤炭分公司,陕西 榆林 719000
- 2. 飞翼股份有限公司,湖南 长沙 410625
- 折叠
摘要
Abstract
In view of the problem of unclear resistance characteristics and difficult transportation of material slurry in Bulianta Coal Mine,an industrial grade ring pipe test system is used to study the resistance characteristics of straight pipes and curved pipes under different concentrations and flow rates.Based on the Bingham plastic fluid model,regression fitting and analysis are carried out on the shear force and viscosity coefficient under different working conditions.The results show that the pressure loss in both the straight pipe and curved pipe sections increases with the increase of material slurry concentration and transportation flow rate,and the material slurry concentration factor has a more significant impact on the pressure loss in the curved pipe section.Overall,the unit pressure loss in the curved pipe section is 12.9-17.8 times than that of the straight pipe section.The regression analysis shows that the Bingham plastic fluid model has good adaptability,with shear forces of 41.50-50.01 Pa and viscosity coefficients of 0.203-0.225 Pa·s.关键词
膏体充填/环管试验/压力损失Key words
paste filling/ring pipe test/pressure loss分类
矿业与冶金引用本文复制引用
田银素,朱阳亚,黄振华..补连塔煤矿膏体充填环管输送试验研究[J].山东煤炭科技,2024,42(8):185-190,6.