| 注册
首页|期刊导航|河南水利与南水北调|某泵站工程水力过渡过程计算分析

某泵站工程水力过渡过程计算分析

张海涵

河南水利与南水北调2024,Vol.53Issue(9):62-63,2.
河南水利与南水北调2024,Vol.53Issue(9):62-63,2.

某泵站工程水力过渡过程计算分析

Calculation and Analysis of Hydraulic Transients in a Pumping Station Project

张海涵1

作者信息

  • 1. 河南省水利勘测设计研究有限公司,河南 郑州 450016
  • 折叠

摘要

Abstract

Combined with the conditions of water supply engineering,the hydraulic transients simulation calculation of water supply pipeline system is made,and the water hammer protection objective is met by selecting economically reasonable engineering measures.After the constant flow calculation of the water supply system and the calculation of the transients of pumping without protection after the pump,the water body with severe negative pressure of the pipeline will be vaporized,which easily lead to the water hammer accident and endanger the safety of the system.Through the calculation and comparison of the air valve protection scheme and the double tower plus air valve protection scheme,the water hammer protection scheme of double tower plus air valve is recommended for this project.

关键词

泵站/过渡过程/水锤/空气阀/单向塔

Key words

pumping station/transients/water hammer/air valve/one-way tower

分类

建筑与水利

引用本文复制引用

张海涵..某泵站工程水力过渡过程计算分析[J].河南水利与南水北调,2024,53(9):62-63,2.