香炉山隧洞竖井600 m级定向钻钻孔施工技术

吴跃帮 张楚 徐峰 杨繁昌 龚贵秋

云南水力发电2024,Vol.40Issue(9):122-125,4.
云南水力发电2024,Vol.40Issue(9):122-125,4.DOI:10.3969/j.issn.1006-3951.2024.09.028

香炉山隧洞竖井600 m级定向钻钻孔施工技术

Construction Technology of 600 m Directional Drilling for Xianglushan Tunnel Vertical Shaft

吴跃帮 1张楚 1徐峰 1杨繁昌 1龚贵秋2

作者信息

  • 1. 中国水利水电第十四工程局有限公司,云南 昆明 650041
  • 2. 云南恒诚建设监理咨询有限公司,云南 昆明 650000
  • 折叠

摘要

Abstract

The vertical shaft of Xianglushan Tunnel in Dali Section I of Central Yunnan Water Diversion Project is a newly added passage.The vertical shaft passes through dolomite limestone and andesite basalt from top to bottom,with prominent problems of karst water inrush and seepage,and high external water pressure.By using directional drilling to implement ground pre grouting for advanced water blocking and reinforcement of the vertical shaft,the safe and rapid excavation of the vertical shaft is ensured.The vertical shaft of Xianglushan Tunnel is constructed using 600m directional drilling.Currently,all drilling has been completed,and the inclination deviation is controlled within 3‰.The technology is feasible and the economic benefits are good.

关键词

香炉山隧洞/竖井/600m/定向钻孔

Key words

Xianglushan Tunnel/vertical shaft/600 m/directional drilling

分类

建筑与水利

引用本文复制引用

吴跃帮,张楚,徐峰,杨繁昌,龚贵秋..香炉山隧洞竖井600 m级定向钻钻孔施工技术[J].云南水力发电,2024,40(9):122-125,4.