陆上换流站联接变区域电气设计研究OA
Research on Electrical Design of Converter Transformer Area in Onshore Converter Station
文章针对陆上换流站换流变区域电气设计进行研究,提出合理的设计方案.在典型的对称单极接线、±500 kV/2 000 MW的方案上,针对联接变区域,对不同变压器容量、型式、接线进行对比分析,对联接变配置、联接变及中性点区域接线、启动回路接线等进行比较.随着深远海海上风电大规模开发,政府退出电价补贴,在典型的对称单极接线、±500 kV/2 000 MW的方案上,文章推荐的陆上换流站联接变区域设备选型及接线型式具有经济性优、可靠性高的优点.联接变采用三相变压器,阀侧中性点经电阻器或电阻器和电抗器接地,启动回路设置在联接变阀侧,联接变阀侧分支回路设置断路器,联接变网侧采用3/2断路器接线且联接变分别入串.
This paper aims at the electrical design research on converter transformer area of a onshore converter station,to put forward a technically and economically reasonable scheme.Different transformer capacities,types and schemes have been compared and analysed based on the converter transformer area of a typical symmetrical unipolar connection,±5 00kV/2 000 MW scheme.And comparison has been done on converter transformer configuration,converter transformer and neutral point connection,pre-insert resistor connection and so on.Converter transformer area equipment selection and scheme of a onshore converter station recommended by this paper has the advantages of excellent economy and high reliability.It is suggested to apply three-phase transformer for converter transformer.Neutral point of the valve side of converter transformer is grounded by resistor or resistor and reactor.The pre-insert resistor is set in the valve side of converter transformer.A circuit breaker is set in each branch of converter transformer.3/2 circuit breaker shcheme is applied in grid side of converter transformer and the converter transformer is connected to the string respectively.
苏成;孔志达;郝为瀚;郭金川;孙仕达;刘生;邹常跃
中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663中国能源建设集团广东省电力设计研究院有限公司,广东 广州 510663南方电网科学研究院有限责任公司,广东 广州 510663
动力与电气工程
海上风电送出陆上换流站联接变压器
offshore wind power transmissiononshore converter stationsystem interconnection transformer
《电力勘测设计》 2024 (9)
10-16,7