This paper mainly introduces the main practice and experience gained through regulatory inspection and control point release for the normal refueling outagel of nuclear power plant organized by the Regional Office.Through strict inspection,it has effectively promoted the long-term stable and safe operation of nuclear power units.It can be used for reference by other Regional Office.

关键词

核电机组/控制点/检查

Key words

nuclear power unit/control point/inspection