老旧燃气管道不停输改造设计OA

Design of Under-pressure Renovation of Old Gas Pipelines

中文摘要英文摘要

以实际工程为例,分析D720 ×7.0和D630 ×7.0的老旧燃气管道水平净距不足、腐蚀穿孔、埋深不足隐患的不停输改造方式.对于水平净距不足的管道,可通过短距离不停输封堵(单封)方式,采用原位换管改造.对于腐蚀穿孔的管道,可通过长距离不停输封堵(双封)方式,采用同沟敷设改造.对于埋深不足的管道,如果具备征地和不停输移动作业条件,选择不停输移动方法改造比较经济;对于征地协调难度大,或施工期要求比较短情况,宜选择不停输封堵方法改造.

Taking an actual project as an exam-ple,the under-pressure renovation methods for the hid-den dangers of insufficient horizontal clearance,corro-sion perforation and insufficient burial depth of old gas pipelines in D720 × 7.0 and D630 × 7.0 are ana-lyzed.For the pipelines with insufficient horizontal clearance,they can be renovated by short-distance un-der-pressure plugging(single plugging)method and in-situ pipe replacement.For the corroded and perfora-ted pipelines,they can be renovated by long-distance under-pressure plugging(double plugging)and laying in the same ditch.For pipelines with insufficient burial depth,if the land requisition conditions are available and the conditions of under-pressure movement opera-tion are available,it is more economical to choose the under-pressure movement method for renovation;For situations where land acquisition coordination is diffi-cult or the construction period is relatively short,it is advisable to choose the method of the under-pressure plugging for renovation.

李磊祚;鲍元飞;韩海;李澜;李洋;左川

中国市政工程华北设计研究总院有限公司 第十设计研究院,天津 300074山东港华燃气集团有限公司,山东济南 250000枣庄市城乡规划设计研究院,山东 枣庄 277100中国市政工程华北设计研究总院有限公司 第四设计研究院,天津 300074

土木建筑

老旧燃气管道改造不停输封堵不停输移动

old gas pipelinerenovationunder-pressure pluggingunder-pressure movement