HDPE管接头方式的选择及施工控制要求OA
Selection of HDPE Pipe Joint Method and Construction Control Requirements
以斯里兰卡康提北供水项目为主要研究对象,该项目HDPE管总长度约为 570 km,管径分别为63 mm、90 mm、110 mm、160 mm、225 mm、280 mm,施工工期为 36 个月,管道沿现有道路边缘敷设,开挖深度1m,针对该项目的设计要求及施工特点,管道接头连接方式的选择及施工控制尤为重要.
This paper focuses on the Kandy North Water Supply Project in Sri Lanka as the main research object.The total length of HDPE pipes in this project is about 570 km,with diameters of 63 mm,90 mm,110 mm,160 mm,225 mm,and 280 mm respectively.The construction period is 36 months,and the pipes are laid along the existing road edge with an excavation depth of 1m.Based on the design requirements and construction characteristics of this project,the selection of pipe …查看全部>>