| 注册
首页|期刊导航|云南水力发电|明挖基坑典型干扰问题处置

明挖基坑典型干扰问题处置

吴健林 段任荣 王耀毅 史伟伟 田冬冬

云南水力发电2024,Vol.40Issue(10):31-35,5.
云南水力发电2024,Vol.40Issue(10):31-35,5.DOI:10.3969/j.issn.1006-3951.2024.10.008

明挖基坑典型干扰问题处置

Disposal of Typical Interference Problems in Open Excavation Foundation Pits

吴健林 1段任荣 1王耀毅 1史伟伟 1田冬冬1

作者信息

  • 1. 中国水利水电第十四工程局有限公司,云南 昆明 650041
  • 折叠

摘要

Abstract

In the process of engineering project management,conflicts in spatial relationships and constraints that do not meet safety protection conditions are often encountered during the construction progress at the project site.These factors bring resistance and uncertainty to the implementation and progress of the engineering project.Therefore,it is necessary to address or standardize the adverse factors encountered from the aspects of engineering treatment measures and management system implementation.Taking the county road relocation,overhead power supply line relocation,ditch relocation,and the handling of the intersection of construction access roads and county roads encountered during the construction process on the project site as examples,this paper summarizes and forms the results.

关键词

交叉干扰/位置关系/迁改/导流

Key words

cross interference/positional relationship/relocation and reform/diversion