云南水力发电2024,Vol.40Issue(10):216-219,4.DOI:10.3969/j.issn.1006-3951.2024.10.047
西山水库坝型比选及堆石重力坝结构设计计算
Comparison and Selection of Dam Types for Xishan Reservoir and Structural Design Calculation of Rockfill Gravity Dam
摘要
Abstract
Xishan Reservoir has unfavorable conditions such as strong weathering and thick rock mass at the dam line,developed cracks,and poor anti-sliding and anti-deformation ability of the right bank mountain.Based on objective conditions such as terrain and geology in the dam site area,this article compares and demonstrates the key technical contents of engineering layout,dam type suitability,construction conditions,and engineering investment between rigid and flexible dams,and designs the optimal gravity dam type with good matching engineering characteristics and economy.The calculation results indicate that the layout scheme of the gravity dam hub is technically feasible and structurally reasonable.The research results can provide technical support for the smooth construction of engineering projects.关键词
坝型比选/重力坝/抗滑稳定/应力分析Key words
comparison and selection of dam types/gravity dam/anti-skid stability/stress analysis分类
建筑与水利引用本文复制引用
孙兆祥,王海波,田锋..西山水库坝型比选及堆石重力坝结构设计计算[J].云南水力发电,2024,40(10):216-219,4.基金项目
重庆市水利科技项目(SLK2023072) (SLK2023072)