新山水库土坝安全评价及除险加固方案分析

邓凌云 王欢

云南水力发电2024,Vol.40Issue(10):220-223,4.
云南水力发电2024,Vol.40Issue(10):220-223,4.DOI:10.3969/j.issn.1006-3951.2024.10.048

新山水库土坝安全评价及除险加固方案分析

Safety Evaluation and Analysis of Reinforcement Plan for the Soil Dam of Xinshan Reservoir

邓凌云 1王欢2

作者信息

  • 1. 贵州省水利水电勘测设计研究院,贵州 贵阳 550002
  • 2. 安徽农业大学工学院土木水利系,安徽 合肥 230036
  • 折叠

摘要

Abstract

Xinshan Reservoir has serious problems such as insufficient flood resistance capacity of the dam,poor quality of soil filling for the dam body,and widespread dispersed infiltration and leakage,which seriously affect the safe and stable operation of flood control and irrigation water supply in the reservoir.To ensure the safe and benign operation of the reservoir,this paper designs and optimizes a risk mitigation and reinforcement plan that combines dam crest elevation and thickening,dam body filling and grouting,and dam foundation shoulder rock curtain grouting based on the current situation of reservoir hazards and safety evaluation conclusions.The results show that the dam reinforcement design scheme is reasonable,and its flood resistance ability has been effectively improved after rectification.The anti-sliding stability of the dam slope and the seepage stability of the dam body meet the requirements of the specifications,and the problem of danger has been effectively solved.The analysis results can provide reference for the anti-seepage and reinforcement of similar dangerous reservoirs.

关键词

均质土坝/坝体渗漏/坝顶加高/帷幕灌浆

Key words

homogeneous earth dam/dam leakage/raise the dam crest/curtain grouting

分类

建筑与水利

引用本文复制引用

邓凌云,王欢..新山水库土坝安全评价及除险加固方案分析[J].云南水力发电,2024,40(10):220-223,4.