| 注册
首页|期刊导航|河南水利与南水北调|一种基于Copula函数的抽水蓄能电站跨年蓄水设计径流计算方法

一种基于Copula函数的抽水蓄能电站跨年蓄水设计径流计算方法

张瀚文 代斌 徐华亭

河南水利与南水北调2024,Vol.53Issue(10):30-31,34,3.
河南水利与南水北调2024,Vol.53Issue(10):30-31,34,3.

一种基于Copula函数的抽水蓄能电站跨年蓄水设计径流计算方法

A Method for Calculating Cross-year Water Storage Design Runoff of Pumped Storage Power Station Based on Copula Function

张瀚文 1代斌 1徐华亭1

作者信息

  • 1. 上海勘测设计研究院有限公司,上海 200335
  • 折叠

摘要

Abstract

The initial water storage period of a pumped-storage power station usually exceeds one year,hence engineering design should account for storage spanning two years and calculate the design runoff for two consecutive years.In the current standard the moving average frequency analysis method is adopted.Although this method ensures the length of the sample series,yet there is strong autocorrelation between the selected samples,which makes it difficult to meet the assumption of sample independence in frequency analysis calculations.In the paper a joint distribution model for the runoff over two consecutive years is established based on Copula function theory to find the solution of the model using a double numerical integration method to obtain the frequency curve.Compared to the traditional method,this method avoids the aforementioned issues while maintaining the sample length and considering the correlation between data series,which is more theoretically appropriate.The case study indicates that there are differences in the design values obtained by different methods in the low-probability segment when calculating the design runoff for two consecutive years.However,for higher probability design results,such as 50%and 75%,the differences are not significant.

关键词

滑动平均频率分析/Copula函数/抽水蓄能电站/初期蓄水

Key words

moving average frequency analysis/Copula functions/pumped-storage power stations/initial storage

分类

建筑与水利

引用本文复制引用

张瀚文,代斌,徐华亭..一种基于Copula函数的抽水蓄能电站跨年蓄水设计径流计算方法[J].河南水利与南水北调,2024,53(10):30-31,34,3.

基金项目

洪水多要素联合分布构建理论及计算方法研究,编号:2022SD(83)-013 (83)

河南水利与南水北调

1673-8853

访问量0
|
下载量0
段落导航相关论文