Abstract
Based on the hydrologic,topographic and geological data of the reach of Qingyuan Pumped Storage Power Station project,the evolution of channel in the reach of the project was analyzed,and the design flood,sediment deposition and backwater analysis were calculated.The possible backwater caused by engineering construction was analyzed.At the same time,the influences of the project construction on the stability of the river regime,the flood carrying capacity of the river,the power generation benefit of 4 small hydropower stations downstream of the project,and the impact of flood control safety and other legitimate water rights of third parties were analyzed.Finally,the comprehensive evaluation opinions and suggestions were proposed.关键词
抽水蓄能电站/洪水影响评价/壅水Key words
pumped storage power station/flood impact assessment/backwater分类
建筑与水利引用本文复制引用
魏建德,訾天亮..庆元抽水蓄能电站洪水影响评价[J].海河水利,2024,(11):27-30,4.