宁夏电力Issue(6):33-38,6.DOI:10.3969/j.issn.1672-3643.2024.06.006
电化学储能电站接入电网测试方法
Testing methods for connecting electrochemical energy storage stations to the power grid
马兵 1刘刚 1张文 1孙大伟 1周玫2
作者信息
- 1. 宁夏电力能源科技有限公司,宁夏银川 750011
- 2. 国网宁夏电力有限公司营销服务中心(国网宁夏电力有限公司计量中心),宁夏银川 750011
- 折叠
摘要
Abstract
With the increasing integration of renewable energy sources,the safe and stable operation of the power grid faces significant challenges.When issues such as active power deficits arise,the precision of power control and response time of renewable energy stations do not meet requirements,hindering their ability to quickly participate in peak shaving and regulate voltage and frequency within the grid.This paper elaborates on the testing methods for connecting electro-chemical energy storage stations to the power grid.It addresses issues such as inappropriate communication configura-tions and unreasonable software logic during testing,proposing corresponding optimization measures like"stop upon reaching limits."Validation of these measures shows that the proposed series of testing optimizations can effectively resolve problems related to excessive response times and inadequate power regulation during testing,significantly enhan-cing the efficiency of testing for energy storage stations connected to the power grid.关键词
储能电站/有功功率/无功功率Key words
energy storage station/active power/reactive power分类
信息技术与安全科学引用本文复制引用
马兵,刘刚,张文,孙大伟,周玫..电化学储能电站接入电网测试方法[J].宁夏电力,2024,(6):33-38,6.