钢模台车在引江补汉输水隧洞出口渐变段中的应用

张可炎 胡其林 王琪 罗伟 张贤

四川水力发电2024,Vol.43Issue(z2):104-107,146,5.
四川水力发电2024,Vol.43Issue(z2):104-107,146,5.

钢模台车在引江补汉输水隧洞出口渐变段中的应用

Application of Steel Formwork Trolley in the Outlet Gradient Transition Section of the Diversion Tunnel from the Yangtze River to the Han River

张可炎 1胡其林 1王琪 1罗伟 1张贤2

作者信息

  • 1. 中国水利水电第五工程局有限公司,四川 成都 610066
  • 2. 宁夏水务投资集团有限公司,宁夏 银川 750000
  • 折叠

摘要

Abstract

The top arch of the outlet gradient transition section of the diversion tunnel from the Yangtze River to the Han River is affected by adverse geological conditions,resulting in excessive settlement and non-conver-gence of the outlet slope of the tunnel.Due to the short period of the construction contract,if the traditional support plane template method is used to pour the edge and top arch,the construction period of the outlet sec-tion cannot meet the safety and schedule requirements of the contract.The article elaborates on the successful application of customized steel formwork trolley in the construction process of the concrete lining for the outlet gradient transition section of the diversion tunnel,which saves 7 days of construction time compared with the flat formwork.The appearance quality of the steel formwork concrete is better than that of the traditional flat large formwork lining for the transition section,which not only saves construction costs but also saves time for subsequent tunnel excavation.The experience and achievements obtained can be used as a reference for similar projects.

关键词

引江补汉/输水隧洞/渐变段/钢模台车/衬砌混凝土

Key words

Water Diversion from the Yangtze River to the Han River/Diversion Tunnel/Gradient section/Steel formwork trolley/Lining concrete