Taking the ore body mining under the tailings pond of Waitou Mountain as the engineering background,the effects of filling mining and open stope method on the surrounding rock were studied.After the on-site investigation and indoor mechanical test in the mining area,the appropriate rock mechanical parameters are selected,a three-dimensional model is established,and then FLAC3D is used to numerically simulate the displacement change,stress distribution and plastic zone position of the stope during the filling and mining process,and the influence on the surrounding rock is compared and analyzed.The results show that after filling the overlying ore body under the tailings pond after mining,the stress of the stope is redistributed,so that the force of the stope structure is more uniform,which effectively limits the displacement of the stope column,avoids the emergence of pastic zone in the top and bottom plate of the stope,and ensures the stability of the stope and its surrounding rock.This research findings provides technical support and data reference for the mine in solving similar problems.

关键词

尾矿库/充填开采/稳定性/数值模拟

Key words

Tailings pond/Backfill mining/Stability/Numerical simulation

分类

数理科学

引用本文复制引用

姜永丰,房祥龙,海龙..歪头山尾矿库下充填开采围岩稳定性分析[J].化工矿产地质,2024,46(4):321-328,8.

基金项目

校级企业委托 歪头山尾矿库下复合膏体充填开采关键技术研究(编号:300221181) (编号:300221181)