露天采矿技术2024,Vol.39Issue(6):74-79,6.DOI:10.13235/j.cnki.ltcm.2024.06.017
安太堡露天矿内排土场扩容边坡稳定性分析
Stability analysis of expanding slope in internal dump of Antaibao Open-pit Mine
李延泽1
作者信息
- 1. 中煤平朔集团有限公司 安太堡露天矿,山西 朔州 036000
- 折叠
摘要
Abstract
To reduce the land area occupied by the external dump of Antaibao Open-pit Mine,the article studies the feasibility of expanding the internal dump under the conditions of anticline structures,proposes two sets of expansion plans for internal dumping based on the analysis of the current inner dumping situation.We construct a geological model of slope engineering based on the latest revised three-dimensional geological model of Antaibao Open-pit Mine,surface condition aerial survey results,and dumping plan design,evaluates the stability of the slopes after the expansion of the internal dump under the two plans for safety using the Spencer and M-P methods of limit equilibrium analysis.The results indicate that expansion plan 1 for the internal dump is more conducive to the safe production and construction of Antaibao Open-pit Mine.关键词
露天矿/内排扩容/背斜/边坡稳定性/极限平衡法Key words
open-pit mine/expanding the internal dump/anticline/slope stability/limit equilibrium method分类
矿业与冶金引用本文复制引用
李延泽..安太堡露天矿内排土场扩容边坡稳定性分析[J].露天采矿技术,2024,39(6):74-79,6.