江淮水利科技Issue(5):49-51,3.DOI:10.20011/j.cnki.JHWR.202405010
影响大型水闸除险加固工程的因素分析
Analysis of factors influencing the hazard prevention and reinforcement of large sluice projects
张丹 1张斌1
作者信息
- 1. 安徽省怀洪新河西坝口闸管理处,安徽 蚌埠 233300
- 折叠
摘要
Abstract
Damaged and hazardous sluice pose significant safety risks in flood prevention and emergency response,threatening the effective operation of the flood control system.Therefore,the hazard prevention and reinforcement of sluice is particularly important.Taking the hazard prevention and reinforcement project of the Xibakou sluice as an example,this study analyzed the factors influencing the reinforcement process,including flood season,engineering operations,monitoring,and construction man-agement.It also proposesd targeted strategies and recommendations.关键词
水闸/除险加固/工程度汛/工程运用/工程监测/建设管理Key words
sluice/risk elimination and reinforcement/engineering flood/engineering application/engineering monitoring/construction management分类
建筑与水利引用本文复制引用
张丹,张斌..影响大型水闸除险加固工程的因素分析[J].江淮水利科技,2024,(5):49-51,3.