设备监理Issue(6):29-33,5.DOI:10.19919/j.issn.2095-2465.2024.12.006
12Cr2Mo1大型锻件性能不合格案例分析
12Cr2Mo1 Large Forging Performance Unqualified Case Analysis
张刘伟 1崔金涛 2王旭锋3
作者信息
- 1. 南京三方化工设备监理有限公司 南京 210000
- 2. 浙江天联机械有限公司 温州 325000
- 3. 洛阳瑞昌环境工程有限公司 洛阳 471000
- 折叠
摘要
Abstract
The purpose of preliminary heat treatment for large forgings is to eliminate forging stress,prevent the occurrence of white spots,refine grain and uniform structure,which is to ensure the final heat treatment and/or cutting performance of forgings,meet the requirements of ultrasonic flaw detection,and conduct heat treatment in advance.Its purpose and process are different from performance heat treatment,and can not be simply cancelled or combined with performance heat treatment.Based on the case of forgings under supervision,this paper analyzes the reasons for the disqualification of forgings after the cancellation of preliminary heat treatment,and puts forward the treatment measures to provide reference for the prevention and treatment of similar quality problems in the follow-up supervision process.关键词
大型锻件/锻后热处理/性能热处理Key words
Large forgings/Preliminary heat treatment/Performance heat treatment分类
通用工业技术引用本文复制引用
张刘伟,崔金涛,王旭锋..12Cr2Mo1大型锻件性能不合格案例分析[J].设备监理,2024,(6):29-33,5.