To satisfy the demand for position correction of prefabricated U-type beams in a subway line,the correction scheme based on jack-ing technology is suggested through the scheme comparison.A complete set of jacking method is established,which specifies the key technolo-gy during the process of jacking correction.Practice shows that the suggested technology has the advantages of high resetting precision,fast construction progress,obvious economic and social benefits,and is worth further popularizing and applying.关键词
梁体纠偏/顶推工法/预制U型梁Key words
Position correction of beam/jacking technology/U-type prefabricated beam分类