Abstract

The process of increasing coal ratio of Masteel B blast furnace is summarized.After B blast furnace's blow-on,a suitable basic operation system is found through groping and adjusting to keep the stable smooth running of the blast furnace.Starting from November 2023,the hot blast furnaces started to be gradually overhauled online and the wind temperature level continued to drop,the coal ratio was further improved by optimizing the upper and lower parts,and the coal ratio reached 165 kg/t in April-May 2024,while the fuel ratio was maintained at below 500 kg/t.

关键词

操作制度/中心加焦/平台加漏斗/煤比

Key words

operation system/central coke charging/platform plus funnel/coal ratio

分类

冶金工业

引用本文复制引用

沈龙龙,高鹏,郝团伟,洪伟,李骏峰,盛敏江..马钢B高炉低风温提煤比实践[J].冶金动力,2025,(1):15-19,5.

冶金动力

1006-6764

访问量0
|
下载量0
段落导航相关论文