| 注册
首页|期刊导航|电力系统自动化|面向调峰需求的热轧负荷可调能力评估方法

面向调峰需求的热轧负荷可调能力评估方法

蔡云帆 徐宪东 余晓丹 贾宏杰 胡枭

电力系统自动化2025,Vol.49Issue(3):1-12,12.
电力系统自动化2025,Vol.49Issue(3):1-12,12.DOI:10.7500/AEPS20231218012

面向调峰需求的热轧负荷可调能力评估方法

Evaluation Method for Adjustable Power Capacity of Hot Rolling Loads for Peak-regulation Demand

蔡云帆 1徐宪东 1余晓丹 1贾宏杰 1胡枭2

作者信息

  • 1. 天津大学电气自动化与信息工程学院,天津市 300072
  • 2. 东北电力大学电气工程学院,吉林省吉林市 132011
  • 折叠

摘要

Abstract

As a typical interruptible load in steel plants,the hot rolling load has great potential in participating in the demands of power grid dispatching and control such as peak regulation.In recent years,with the successive introduction of demand-side electricity market policies,it is urgent to evaluate the regulation capacity of hot rolling loads while fully considering production characteristics and peak regulation service requirements.First,according to the production characteristics of multi-line,multi-product and continuous production of hot rolling loads,a multi-line model of hot rolling loads is established considering the demands of power grid dispatching and control.Then,on this basis,the correlation demand between the electricity peak regulation market and the production energy optimization in the hot rolling process is analyzed,and a comprehensive evaluation method for the adjustable power capacity is proposed,which takes into account both the peak regulation and cost constraints of multi-line hot rolling loads.Finally,the effectiveness of the proposed method is verified through the simulation case analysis,and the capacity,cost and key influencing factors of hot rolling loads participating in intra-day and day-ahead peak-regulation markets are analyzed.

关键词

调峰/热轧负荷/电力市场/评估/生产约束/电网调控

Key words

peak regulation/hot rolling load/electricity market/evaluation/production constraint/power grid dispatching and control

引用本文复制引用

蔡云帆,徐宪东,余晓丹,贾宏杰,胡枭..面向调峰需求的热轧负荷可调能力评估方法[J].电力系统自动化,2025,49(3):1-12,12.

基金项目

国家重点研发计划资助项目(2023YFB2407300) (2023YFB2407300)

国家自然科学基金青年基金资助项目(52107119). This work is supported by National Key R&D Program of China(No.2023YFB2407300)and National Natural Science Foundation of China(No.52107119). (52107119)

电力系统自动化