Abstract
An introduction was made on the planning and design of auxiliary water supply and drainage system for Wudongde Hydropower Station.The production water plant has a large water production capacity since it not only undertakes the construction water,production water and fire water of the underground powerhouse,but also en-sures domestic water of nearby areas.Therefore,the design was optimized by adding a DN500 gravity flow water in-take pipe from the No.1 flood spillway tunnel to the production water plant,which is mutual backup with the origi-nal water intake scheme.Domestic water plant is designed with frame water intake tower,and mainly supplies wa-ter to the high and low areas of the living camp.Sewage treatment stations are equipped with buried integrated A/O equipment,which are respectively installed at the relative concentrated positions of dispersed areas to recycle and treat domestic sewage.关键词
辅助供排水系统/规划设计/优化设计/乌东德水电站Key words
auxiliary water supply and drainage system/planning and design/optimize design/Wudongde Hydro-power Station分类
建筑与水利