燃气管道水平定向钻穿越富水山体注浆止水技术
Grouting Leak-stoppage Technology for Gas Pipeline Horizontal Directional Drilling Crossing Water-rich Mountain
刘兵 1田建禹 1李浩然1
作者信息
- 1. 北京城建亚泰建设集团有限公司,北京 100013
- 折叠
摘要
Abstract
In view of the water gushing phenomenon en-countered during a gas pipeline horizontal directional drilling crossing water-rich mountain in Beijing,the grouting leak-stoppage technology for horizontal direc-tional drilling crossing water-rich mountain was devel-oped,which achieved good leak-stoppage effect.The groundwater of water-rich mountain is mainly the bed-rock fissure water.According to the situation of the ex-ploration hole,the position of the water outlet point is determined,and the grouting packer is sent to the pre-determined position in the guide hole for seat sealing.The grouting material is injected into the blocked guide hole with the pressure higher than the bedrock fissure water,so that the grouting material fills the bed-rock fissure of the water-rich mountain.After the final solidification of the grouting material,the bedrock fis-sure can be sealed and the leak can be stopped.关键词
水平定向钻/富水山体/注浆止水/注浆材料Key words
horizontal directional drilling,water-rich mountain,grouting leak-stoppage/grouting material分类
建筑与水利引用本文复制引用
刘兵,田建禹,李浩然..燃气管道水平定向钻穿越富水山体注浆止水技术[J].煤气与热力,2025,45(2):85-87,3.