| 注册
首页|期刊导航|水力发电|隧道CD法施工不同开挖台阶长度对围岩稳定的影响

隧道CD法施工不同开挖台阶长度对围岩稳定的影响

赵树林 孟令东 刘中欣 张万里 杨永军 危君安 刘佳怡

水力发电2025,Vol.51Issue(3):64-70,7.
水力发电2025,Vol.51Issue(3):64-70,7.

隧道CD法施工不同开挖台阶长度对围岩稳定的影响

Influence of Different Step Lengths on the Stability of Surrounding Rock in Tunnel CD Method Construction

赵树林 1孟令东 2刘中欣 3张万里 3杨永军 3危君安 4刘佳怡5

作者信息

  • 1. 新疆乌京铁建轨道交通有限公司,新疆 乌鲁木齐 830011
  • 2. 北京市轨道交通建设管理有限公司,北京 100068
  • 3. 中铁十五局集团城市轨道交通工程有限公司,广东 广州 510400
  • 4. 上海先行建设监理有限公司,上海 200070
  • 5. 新疆大学,新疆 乌鲁木齐 830017
  • 折叠

摘要

Abstract

In order to simulate the excavation process of CD method construction of a class V rock tunnel,the FLAC3D software is used to design four kinds of excavation step lengths,such as 3,5,7 m and 9 m,and the variation rules of the surrounding rock settlement and the horizontal convergence,stress and plastic zone under four kinds of excavation steps are compared from three aspects of the deformation characteristics of surrounding rock,the characteristics of load distribution and the changes in the damage of surrounding rock.The results show that,(a)in the early stage of excavation,the surrounding rock settlement rate is fast,the deformation is significant near the excavation surface with a gradient distribution,and under different step lengths,the trends of surrounding rock settlement and horizontal convergence are similar and gradually increase with the increase of step length;(b)the surrounding rock force is non-linear,the stress near the excavation surface is concentrated,and away from the excavation surface the stress is gradually reduced;and(c)with the increase of step length,the surrounding rock damage increases,which is mainly tensile damage,and the appropriate reduction of step length can narrow the damage range.

关键词

隧道/CD法施工/台阶长度/围岩变形/荷载分布/损伤变化/数值模拟

Key words

tunnel/CD method/different step length/deformation of surrounding rock/load distribution/damage change/numerical simulation

分类

建筑与水利

引用本文复制引用

赵树林,孟令东,刘中欣,张万里,杨永军,危君安,刘佳怡..隧道CD法施工不同开挖台阶长度对围岩稳定的影响[J].水力发电,2025,51(3):64-70,7.

基金项目

国家自然科学基金地区科学基金资助项目(52068-066) (52068-066)

自治区高校基本科研业务费科研项目-培育类项目(XJEDU202-3P010) (XJEDU202-3P010)

水力发电

0559-9342

访问量1
|
下载量0
段落导航相关论文