In this paper,the characteristics and application of heavy hoisting equipment that can be used in the construction of third-generation nuclear power plants in China are analyzed,and taking the third-generation nuclear power plants made in China as an example,the requirements for hoisting stations,hoisting capacity,equipment investment,basic investment,comprehensive usage fee and social benefits of different heavy hoisting equipment options for the general layout of nuclear power plants are compared.Finally,the heavy hoisting equipment suitable for the construction of domestic third-generation nuclear power plants is summarized.关键词
核电站/建造阶段/起重设备/费用分析/选型Key words
nuclear power plant/construction stage/hoisting equipment/cost analysis/type selection分类