首页|期刊导航|北京水务|基于HEC-RAS的永定河石景山麻峪以北防洪堵口洪水风险分析

基于HEC-RAS的永定河石景山麻峪以北防洪堵口洪水风险分析

张超 贾梦琳 黄敬梅 孙梦超 刘芳

北京水务Issue(1):7-13,7.
北京水务Issue(1):7-13,7.DOI:10.19671/j.1673-4637.2025.01.002

基于HEC-RAS的永定河石景山麻峪以北防洪堵口洪水风险分析

Risk analysis of flood inundation in north of Mayu Village of Yongding River based on HEC-RAS

张超 1贾梦琳 1黄敬梅 2孙梦超 1刘芳1

作者信息

  • 1. 北京市水利规划设计研究院 北京 100048
  • 2. 北京市水资源调度管理事务中心 北京 101117
  • 折叠

摘要

Abstract

In the Haihe River Basin,the"23·7"torrential rain event caused a flood in Yongding River from the section of Sanjiadian Regulation Pool to the Lugouqiao Flood Diversion Hub with a recurrence in-terval exceeding 50 years.To enhance flood control and emergency response capabilities,a two-dimen-sional hydrodynamic model(HEC-RAS)was employed to simulate and analyze the flood evolution and in-undation patterns under different flood frequencies in the northern part of Mayu Village,Lusan Section of the Yongding River.The results indicated that the left bank of the Sanjiadian regulating pool did not over-flow during or less a 200-year flood event at the Sanjiadian barrage.Moreover,the flood was largely con-fined to the west area of the Fengsha Railway for flood events with recurrence intervals greater than 200 years.Based on these findings,the optimal timing for flood control interventions at four strategic locations of north Mayu along the Yongding River was proposed.The study provides a valuable decision-making framework for flood control and emergency response operations.

关键词

永定河/HEC-RAS/洪水淹没/风险分析/防洪工程

Key words

Yongding River/HEC-RAS/flood inundation/risk analysis/flood control engineering

分类

水利科学

引用本文复制引用

张超,贾梦琳,黄敬梅,孙梦超,刘芳..基于HEC-RAS的永定河石景山麻峪以北防洪堵口洪水风险分析[J].北京水务,2025,(1):7-13,7.