东北水利水电2025,Vol.43Issue(3):20-22,48,4.
水库导流洞封堵设计与施工关键问题探讨
Key problems discussion on design and construction of reservoir diversion tunnel closure
吕春雨1
作者信息
- 1. 兴城市水利事务服务中心,辽宁葫芦岛 125100
- 折叠
摘要
Abstract
Diversion tunnel plugging project directly affects the project quality,normal operation and operation life of water conservancy projects.The rationality of its engineering design and the smooth and timely completion of plugging work have an important impact on the subsequent project progress and whether the project can exert benefits in time.In this paper,several key problems in the design and construction technology of reservoir diversion tunnel are discussed in depth,and the technical scheme of plugging construction of a reservoir diversion tunnel in Huludao,Liaoning is analyzed in detail.关键词
导流洞/封堵/设计/施工技术Key words
diversion tunnel/plugging/design/construction technology分类
水利科学引用本文复制引用
吕春雨..水库导流洞封堵设计与施工关键问题探讨[J].东北水利水电,2025,43(3):20-22,48,4.