首页|期刊导航|东北水利水电|水库导流洞封堵设计与施工关键问题探讨

水库导流洞封堵设计与施工关键问题探讨OA

Key problems discussion on design and construction of reservoir diversion tunnel closure

中文摘要英文摘要

导流洞封堵工程直接影响水利工程的工程质量、正常运行和运行寿命,其工程设计的合理性与封堵工作的顺利完成,对后续的工程进度和工程能否及时发挥效益有着重要影响.本文主要针对水库导流洞设计和施工技术方面的几个关键问题进行了深入探讨,并详细分析了辽宁葫芦岛某水库导流洞封堵施工技术方案.

Diversion tunnel plugging project directly affects the project quality,normal operation and operation life of water conservancy projects.The rationality of its engineering design and the smooth and timely completion of plugging work have an important impact on the subsequent project progress and whether the project can exert benefits in time.In this paper,several key problems in the design and construction technology of reservoir diversion tunnel are discussed in depth,and the technical scheme of plugging construction of a reservoir diversion tunnel in Huludao,Liaoning is analyzed in detail.

吕春雨

兴城市水利事务服务中心,辽宁葫芦岛 125100

水利科学

导流洞封堵设计施工技术

diversion tunnelpluggingdesignconstruction technology

《东北水利水电》 2025 (3)

20-22,48,4