Abstract
Yingtang Sluice is demolished and reconstructed to restore its designed water diversion capacity,eliminate the safety hazards of dangerous culvert sluice,and ensure the safety of flood control.For the selection of characteristic water level of Yingtang Sluice,both the designed water diversion level under current situation and the designed water diversion level under the maximum scouring of the Yellow River are considered;for the determination of the sluice floor elevation,the interrelationship between the floor elevation,gate hole width and sluice hole number are comprehensively considered;and the foundation treatment method is determined based on the features of the Yellow River Diversion Project.The engineering design of Yingtang Sluice Reconstruction Project has important reference value for the subsequent culvert sluice reconstruction.关键词
工程设计/特征水位/闸室稳定/结构计算Key words
engineering design/characteristic water level/stability of sluice chamber/structural calculation分类
建筑与水利引用本文复制引用
李志锋,张庆杰..影唐闸改建工程闸室稳定计算要点分析[J].河南水利与南水北调,2025,54(1):54-55,59,3.