江苏水利Issue(3):59-61,3.
刘山站节制闸卷扬式启闭机改造技术探讨
Discussion on the renovation technology of the gate lifting hoist for the control gate at Liushan Station
摘要
Abstract
This article focuses on the overload problem of the gate lifting hoist for the control gate of Liushan Station in the south-to-north water diversion project.The cause is attributed to the need for further consideration of the additional load caused by the impact of the downstream water flow on the main beam of the gate during reverse water blocking,in addition to the usual selection based on the forward water blocking gate lifting force.Based on the above reasons,by re-selecting and calculating,replacing the matching motor and corresponding reducer,the problem of motor overload can be completely solved.The research findings can serve as a reference for the optimal selection of gate lifting hoists for control gates and their technical renovation.关键词
水利工程/节制闸/卷扬式启闭机Key words
water conservancy project/control gate/gate lifting hoist分类
建筑与水利引用本文复制引用
葛浩,沙福全,王泽忠,李蕴升,戴义,于贤磊..刘山站节制闸卷扬式启闭机改造技术探讨[J].江苏水利,2025,(3):59-61,3.基金项目
江苏南水北调科技研发项目(JSNSBD202201) (JSNSBD202201)