四川水力发电2025,Vol.44Issue(1):10-15,6.DOI:10.20196/j.cnki.scslfd.20250104
金沙江银江水电站砂石加工系统生产工艺的调整
Process Adjustment of Sandstone Processing System of Yinjiang Hydropower Project on Jinsha River
罗文起 1代瑞丹1
作者信息
- 1. 中国水利水电第七工程局有限公司,四川 成都 610213
- 折叠
摘要
Abstract
With the dramatic changes in the aggregate source of the sandstone processing system at Yinjiang Hydropower Project,the original system that applied to produce and process new material sources has resulted in many problems such as low productivity,poor quality of made aggregates,the ineffective feedback of wastewater treatment systems,and increased production costs.Therefore,it is necessary to adjust the system process to adapt to the processing of new material sources.This paper describes the adjustments made to the production process of the sand and gravel processing system.关键词
银江水电站/砂石加工系统/料源/重大变更/质量不达标/工艺调整Key words
Yinjiang Hydropower Project/Sandstone processing system/Aggregate source/Dramatic change/Substandard product quality/Process adjustment分类
水利科学引用本文复制引用
罗文起,代瑞丹..金沙江银江水电站砂石加工系统生产工艺的调整[J].四川水力发电,2025,44(1):10-15,6.