四川水力发电2025,Vol.44Issue(1):25-30,83,7.DOI:10.20196/j.cnki.scslfd.20250107
银江水电站全水头运行贯流式机组的设计
Design of Full-head Tubular Set for Yinjiang Hydropower Project
郭学洋 1杨锐 2张祝年3
作者信息
- 1. 长江勘测规划设计研究有限责任公司,湖北 武汉 430010
- 2. 攀枝花华润水电开发有限公司,四川 攀枝花 617067
- 3. 四川川投能源股份有限公司,四川 成都 610044
- 折叠
摘要
Abstract
This article introduces the process of selecting and designing the tubular unit of Yinjiang Hydropower Project,and optimizing the hydraulic development of the turbine.The performance parameters of the unit fi-nally design meet or exceed the contract requirements,and are suitable for the complex tailwater level condi-tions and low head flood discharge of Yinjiang Power Project.The bulb tubular turbine generator set with the largest single unit capacity and the largest runner diameter has been developed in China.关键词
银江水电站/全水头/选型/设计/最大灯泡贯流式水轮发电机组Key words
Yinjiang Hydropower Project/Full-head/Selection/Design/Largest bulb tubular turbine generator set分类
水利科学引用本文复制引用
郭学洋,杨锐,张祝年..银江水电站全水头运行贯流式机组的设计[J].四川水力发电,2025,44(1):25-30,83,7.