四川水力发电2025,Vol.44Issue(1):41-45,78,6.DOI:10.20196/j.cnki.scslfd.20250110
综合物探技术在银江水电站灌浆工程质量评价中的应用
Application of Comprehensive Geophysical Exploration Technology in Quality Evaluation of Grouting Engineering at Yinjiang Hydropower Project
陈爽爽 1魏仁新 1凌巍 1蔡加兴2
作者信息
- 1. 长江地球物理探测(武汉)有限公司,湖北 武汉 430014
- 2. 长江勘测规划设计研究有限责任公司,湖北 武汉 430014
- 折叠
摘要
Abstract
In order to improve the physical and mechanical properties of shallow and geologically defective rock masses,enhance their uniformity,integrity,and impermeability,a large amount of consolidation grouting and curtain grouting have been carried out in the dam site area of Yinjiang Hydropower Project.To ensure the con-struction quality of grouting engineering,comprehensive geophysical techniques such as single hole acoustic wave method,borehole panoramic imaging,and water pressure test were used to comprehensively detect and e-valuate the grouting quality.The application results show that comprehensive geophysical techniques such as using single hole acoustic wave method to compare and analyze the characteristic values and changing trends of rock wave velocity before and after grouting,observing the development of rock structural planes and cement stone filling in the borehole wall through panoramic imaging,and analyzing the permeability of rock mass through water pressure test can comprehensively evaluate the construction quality of grouting engineering and provide a basis for the acceptance of concealed engineering.关键词
银江水电站/灌浆质量评价/综合物探/单孔声波/钻孔全景成像/压水试验Key words
Yinjiang Hydropower Project/Grouting quality evaluation/Comprehensive geophysical exploration/Single hole acoustic wave/Panoramic imaging of drilling holes/Pressure water test分类
建筑与水利引用本文复制引用