科技创新与应用2025,Vol.15Issue(8):156-159,4.DOI:10.19981/j.CN23-1581/G3.2025.08.035
南京地铁车辆主熔断器熔断后对整车的影响研究
王亚栋1
作者信息
- 1. 南京地铁运营有限责任公司,南京 210000
- 折叠
摘要
Abstract
This paper mainly introduces the impact of the main fuse blowing in the vehicle traction system of the ALSTOM project model of Nanjing Metro Line 2.Emphasis is placed on the detailed explanation of the traction high-breaking and closing authorization of the TCMS system and the pre-charging management logic of the traction system,and the corresponding design scheme is proposed.关键词
地铁/主熔断器/TCMS/高断闭合授权/预充电Key words
metro/main fuse/TCMS/high-break closing authorization/pre-charging分类
交通工程引用本文复制引用
王亚栋..南京地铁车辆主熔断器熔断后对整车的影响研究[J].科技创新与应用,2025,15(8):156-159,4.