首页|期刊导航|水力发电|抽水蓄能电站地下洞室群开挖支护方案优化研究

抽水蓄能电站地下洞室群开挖支护方案优化研究

李仁杰 江浩 苏国韶 刘海滨 陈贤杰

水力发电2025,Vol.51Issue(4):54-61,8.
水力发电2025,Vol.51Issue(4):54-61,8.

抽水蓄能电站地下洞室群开挖支护方案优化研究

Optimization of Excavation and Support Schemes for Underground Caverns of Pumped-storage Power Station

李仁杰 1江浩 1苏国韶 2刘海滨 2陈贤杰2

作者信息

  • 1. 山东电力工程咨询院有限公司,山东 济南 250013
  • 2. 广西大学土木建筑工程学院,广西 南宁 530004
  • 折叠

摘要

Abstract

Using the numerical simulation method of FLAC3D,this study optimizes the excavation elevation,excavation sequence and support scheme for the underground caverns of a pumped-storage power station.The results show that,(a)the underground caverns are dominated by horizontal structural stresses,and minor changes in the excavation elevation and have a minimal impact on the stability of the surrounding rock;and(b)compared to the worst scheme of excavation sequence,the optimal scheme results in a smaller depth of the plastic zone of arch seat downstream of the main powerhouse,with no connection to the plastic zone of downstream wall,and a reduction in the maximum displacement at the intersection of main powerhouse and bus-bar tunnels.Furthermore,based on the numerical calculation results of original support scheme,local support optimization is conducted for the main powerhouse,bus-bar tunnels,and tailrace sluice chamber.After optimization,the problem of plastic zone connectivity between the surrounding rock of main powerhouse and transformer chamber,as well as between the bus-bar tunnels,is resolved.The volume of plastic zone of surrounding rock is decreased by 17%,and the maximum displacement of surrounding rock is decreased by 7%,which significantly improves the stability of surrounding rock.

关键词

抽水蓄能电站/地下洞室群/开挖支护/方案优化

Key words

pumped-storage power station/underground caverns/excavation and support/scheme optimization

分类

建筑与水利

引用本文复制引用

李仁杰,江浩,苏国韶,刘海滨,陈贤杰..抽水蓄能电站地下洞室群开挖支护方案优化研究[J].水力发电,2025,51(4):54-61,8.