一起1000 kV隔离开关异常分合闸事故分析

杨奇 孙法治

东北电力技术2025,Vol.46Issue(4):52-54,59,4.
东北电力技术2025,Vol.46Issue(4):52-54,59,4.

一起1000 kV隔离开关异常分合闸事故分析

Analysis of Abnormal Opening and Closing Event of 1000 kV Isolating Switch

杨奇 1孙法治2

作者信息

  • 1. 山西潞光发电有限公司,山西 长治 046600
  • 2. 国网营口大石桥市供电公司,辽宁 营口 115100
  • 折叠

摘要

Abstract

In view of the mis-opening and closing accident of a 1000 kV isolating switch during the local opening after the motor being burnt during the closing process,it analyzes the problems in the application range of auxiliary contacts in different time sequence and the control circuit of isolation switch with single-phase linkage and separate phase operation.It proposes solutions to strengthen the re-quirements of the isolating switch control circuit,clarify the action timing of the auxiliary contacts of the isolating switch,optimise the relationship between the self-holding control circuit and the motor power circuit,and standardise the operational processes of mainte-nance personnel,ensuring the safe and stable operation of the isolating switch,providing a reference for the circuit design and opera-tion maintenance of similar isolating switches.

关键词

隔离开关/辅助触头/时序图/自保持

Key words

isolating switch/auxiliary contacts/time sequence diagram/self-holding