高压电器2025,Vol.61Issue(4):39-46,53,9.DOI:10.13296/j.1001-1609.hva.2025.04.005
特高压换流站主设备运行状态抗震性能评估
Seismic Performance Assessment of Main Equipment of UHV Converter Station in Operation Condition
张世洪 1李浩丹 1杨应山 1梁晨1
作者信息
- 1. 中国南方电网有限责任公司超高压输电公司大理局,云南 大理 671000
- 折叠
摘要
Abstract
The seismic performance of the main equipment of UHV(ultra-high voltage)converter station in seismic-prone area is related to safety and stability of the transmission system under long-term operation.In this paper,the seismic performance of the main equipment of a specific UHV converter station is systematically classified,the as-sessment method for the seismic performance of the main equipment under the operating condition is proposed.The operation and maintenance strategy of typical±800 kV UHV DC(direct current)wall bushing equipment is studied and the seismic performance assessment method of the main equipment of the UHV converter station under the oper-ating condition is assessed.The results show that the main equipment of the converter station can adopt differentiated seismic performance assessment strategies according to different categories,and the main equipment with damping measures needs subjecting to mechanical performance tests so to ensure the safety of its structure.The seismic perfor-mance assessment method of main equipment of the converter station under operating condition includes finite ele-ment analysis,on-site test,structure test,and comprehensive comparison and analysis.The operation and mainte-nance strategy can adopt the routine and professional operation and maintenance strategy.The method based on on-line monitoring is helpful in better assessing the overall operation condition of the converter station.关键词
特高压换流站/电气设备/抗震性能/评估方法/现场测试Key words
UHV converter station/electrical equipment/seismic performance/assessment method/on-site test引用本文复制引用
张世洪,李浩丹,杨应山,梁晨..特高压换流站主设备运行状态抗震性能评估[J].高压电器,2025,61(4):39-46,53,9.