| 注册
首页|期刊导航|云南水力发电|两河口水电站输水系统充水试验分析

两河口水电站输水系统充水试验分析

晏明 王红军

云南水力发电2025,Vol.41Issue(4):31-35,5.
云南水力发电2025,Vol.41Issue(4):31-35,5.DOI:10.3969/j.issn.1006-3951.2025.04.008

两河口水电站输水系统充水试验分析

Analysis of Water Filling Test for the Water Transmission System of Lianghekou Hydropower Station

晏明 1王红军1

作者信息

  • 1. 中国水利水电第十四工程局有限公司,云南 昆明 650041
  • 折叠

摘要

Abstract

The geological conditions of the Lianghekou Hydropower Station project are complex,located in a high stress,cold and high-altitude area.The water filling test of high head water conveyance system is an indispensable safety inspection item for the operation of power stations.It is a process of loading,unloading,inspection,monitoring,problem discovery and defect treatment,and the first safety inspection of the water conveyance system after construction is completed.The success of the water filling and drainage test is the most important and fundamental condition for the commissioning of power plant units.By conducting water filling and drainage tests on the water supply system,it is possible to ensure the achievement of the scheduled power generation target and create conditions for unit commissioning.

关键词

水电站/引水系统/尾水系统/充水试验

Key words

hydropower station/water diversion system/tail water system/water filling test

分类

建筑与水利

引用本文复制引用

晏明,王红军..两河口水电站输水系统充水试验分析[J].云南水力发电,2025,41(4):31-35,5.