首页|期刊导航|科技创新与应用|超浅覆软土地层高铁大直径泥水盾构接收技术研究

超浅覆软土地层高铁大直径泥水盾构接收技术研究

刘彦良

科技创新与应用2025,Vol.15Issue(12):161-164,4.
科技创新与应用2025,Vol.15Issue(12):161-164,4.DOI:10.19981/j.CN23-1581/G3.2025.12.037

超浅覆软土地层高铁大直径泥水盾构接收技术研究

刘彦良1

作者信息

  • 1. 中铁十四局集团有限公司,济南 250000
  • 折叠

摘要

Abstract

The exit section of the shield shield of the Zhanjiang Bay Subsea Tunnel Project is mainly in soft soil formation,and the soil depth at the shallowest part of the formation is only 4.6 m.In view of the construction risks brought by the ultra-shallow soil formation,pre-reinforcement measures for the ultra-shallow soil formation are proposed.The reinforcement area of the receiving section adopts deep-hole grouting,pile foundation cover plate and triaxial mixing piles full reinforcement measures.The end of the shield receiving shaft adopts comprehensive reinforcement measures of triaxial mixing piles+cement mortar ground connecting walls+high-pressure rotary grouting to improve the soil strength and strictly control the shield parameters.To ensure the construction safety of the shield during receiving,the engineering practice results show that the attitude of the shield is well controlled after receiving,and the surface settlement is within the control value range.The pre-reinforcement measures in this paper can be used for receiving the shield under similar ultra-shallow soil-covered stratum conditions.Provide reference for construction.

关键词

盾构接收/超浅覆土/预加固/掘进参数/地表监测

Key words

shield receiving/ultra-shallow soil covering/pre-reinforcement/excavation parameter/surface monitoring

分类

交通工程

引用本文复制引用

刘彦良..超浅覆软土地层高铁大直径泥水盾构接收技术研究[J].科技创新与应用,2025,15(12):161-164,4.