四川水力发电2025,Vol.44Issue(2):71-75,80,6.DOI:10.20196/j.cnki.scslfd.20250218
春厂坝闸首源网荷储一体化示范项目研究
Research of Chunchangba Hydropower Project Source-Grid-Load-Storage Integration Demonstration Project
王伟 1薛玉林1
作者信息
- 1. 阿坝水电开发有限公司,四川 黑水 623503
- 折叠
摘要
Abstract
Under the strategic goal of"dual carbon",building a new power system is the only way to achieve carbon peak and carbon neutrality.Among them,cultivating a new business model of distributed source-grid-load-storage integration(SGLS)is one of the important measures.Taking the power supply mode and load de-mand scenario of the gatehead of Chunchangba Hydropower Project,this paper introduces in detail the practical application of SGLS with the characteristics of"diesel-PV-storage-charging"integrated self-contained power supply,mainly including the complementary utilization and joint control strategy research of SGLS under the integration of local power grid,diesel generators,solar photovoltaic components,parallel grid bidirectional con-verters,energy storage batteries,automatic transfer devices,charging piles,spillway gate equipment,etc.Under the premise of meeting the reliability of power supply,the utilization of new energy is improved to achieve cost-effective synergistic operation.关键词
新能源/源网荷储/柴光储充/联合控制/经济优化Key words
New energy/Source-grid-load-storage/Diesel-PV-storage-charging/Joint control/Cost-effective opti-mization分类
信息技术与安全科学引用本文复制引用