四川水力发电2025,Vol.44Issue(2):126-130,5.DOI:10.20196/j.cnki.scslfd.20250230
某大型水电站导叶端面间隙偏小原因分析及处理措施
Analysis on the Causes of the Small Clearance at the End Surface of the Guide Vane of a Large Hydropower Project and Its Treatment Measures
杨超1
作者信息
- 1. 四川小金川水电开发有限公司,四川 成都 610072
- 折叠
摘要
Abstract
The main process of the installation of the water guide mechanism of a large sized hydropower project is introduced,the reason for the small clearance on the end surface of the guide vane during the installation of the guide vane mechanism of Unit 1 is analysed,and economical and feasible treatment measures are proposed.At the same time,before machining the seat ring,the impact of the actual processing size of the top cover,the amount of sinking of the top cover and other factors should be carefully measured and analysed,and the pro-cessing size of each processing surface of the seat ring should be determined to ensure that the total clearance at the end surface of the guide vane meets the design requirements after the installation of the water guide mecha-nism is completed.关键词
座环/顶盖/导水机构/导叶档体/三维测量Key words
Seat ring/Top cover/Water guide mechanism/Guide vane clearance/Three-dimensional measure-ment分类
水利科学引用本文复制引用
杨超..某大型水电站导叶端面间隙偏小原因分析及处理措施[J].四川水力发电,2025,44(2):126-130,5.