江苏水利Issue(5):38-41,4.
淮河入海水道二期工程堤防填筑泓土料碾压工艺分析
Analysis of the rolling compaction process of the embankment filling of the Second Phase of the Huaihe River to the Sea Waterway Project
摘要
Abstract
The on-site river embankment filling and compaction test is one of the effective ways to obtain reasonable construction parameters.The optimal compaction construction scheme determined through the on-site compaction test can scientifically and effectively guide the embankment filling construction and ensure the construction quality of the embankment filling.Taking the river embankment filling construction project of the Yancheng section in the second phase of the Huaihe River to the Sea Waterway as an example,through analyzing the process and results of the on-site compaction test of the Hong earth materials,the laying thickness and the time of compaction for the filling construction of these soil materials have been determined.This provides powerful data support for the filling construction of this project,and also serves as a reference for other similar embankment filling projects using Hong earth materials.关键词
堤防填筑/碾压试验/泓土料/铺设厚度/碾压遍数Key words
embankment filling/rolling compaction test/Hong earth material/laying thickness/times of compaction分类
水利科学引用本文复制引用
钱彬,占鑫杰,许小龙,张成..淮河入海水道二期工程堤防填筑泓土料碾压工艺分析[J].江苏水利,2025,(5):38-41,4.基金项目
江苏省水利科技项目(2023033) (2023033)