| 注册
首页|期刊导航|江苏水利|坝坡土工膜损伤对水库坝体边坡安全稳定的影响

坝坡土工膜损伤对水库坝体边坡安全稳定的影响

黄瑶 陈闯 杨青森 颜泽群 司帅

江苏水利Issue(5):47-52,6.
江苏水利Issue(5):47-52,6.

坝坡土工膜损伤对水库坝体边坡安全稳定的影响

Influence of geomembrane defects on dam slopes on the safety and stability of reservoir embankments

黄瑶 1陈闯 2杨青森 2颜泽群 1司帅1

作者信息

  • 1. 江苏省鸿源招标代理股份有限公司,江苏 宿迁 213800
  • 2. 宿迁市水务勘测设计研究有限公司,江苏 宿迁 223899
  • 折叠

摘要

Abstract

In order to explore the influence rules of the geomembrane defects on the upstream dam slope of the reservoir and the length of the horizontal damage on the downstream side on the safety and stability of the dam,this problem is studied through the finite element calculation and simulation method.The following conclusions are obtained:The occurrence of defects in the geomembrane on the upstream dam slope of the reservoir will cause seepage deformation of the embankment and lead to damage at the downstream toe of the dam.Moreover,the length of the damage at the downstream toe of the dam has a significant impact on the overall safety and stability of the dam.In addition,the defect area of the geomembrane on the upstream dam slope corresponding to the allowable seepage gradient at the seepage exit point of the dam slope is 0.45 square meters.Under the condition of this defect area,as the length of the downstream horizontal damage increases,the minimum safety and stability coefficient of the downstream slope will continuously decrease.The critical value of the length of the horizontal damage at the downstream toe of the dam,at which the dam structure becomes unstable,is 14.28 meters.The research results of this study can provide a reference for related projects.

关键词

大坝安全/土工膜缺陷/下游破坏长度/有限元计算

Key words

dam safety/geomembrane defects/downstream damage length/finite element calculation

分类

建筑与水利

引用本文复制引用

黄瑶,陈闯,杨青森,颜泽群,司帅..坝坡土工膜损伤对水库坝体边坡安全稳定的影响[J].江苏水利,2025,(5):47-52,6.